OpenNov 22, 2026
No due date
•Last updated Goal (owner 2026-10-22, runs in parallel with M1 and M3): Company OS matches or exceeds the leading open-source agent-company orchestrators, so real company workflows can run on it end to end: create a company, hire agents into roles, set goals, assign tasks, heartbeats run on schedule, budgets are enforced, approvals gate actions, and every step is in the audit trail. Exit: that workflow runs end to end on a live install with host evidence; every capability gap from the parity review is closed or explicitly ruled out by the owner.
Phases, in order (filter issues with label phase:M2.N):
- M2.1 (label phase:M2.1) Company and company boundaries. Done when: A company can be created, archived and restored from the UI, and a non-member never sees another company's agents, org chart, work items, work products or secrets (tests)
- M2.2 (label phase:M2.2) Hire agents onto a working org chart. Done when: An agent hired from the UI can be heartbeat-enabled in the hire flow or agent settings, migrated CEO agents are schedulable, and every person and agent has a manager or is a deliberate root
- M2.3 (label phase:M2.3) Goals and work hierarchy. Done when: Goals, portfolios, programs and boards can be edited and archived from the UI, and the work-item hierarchy rules (parent type, same company, no cycles) are enforced (tests)
- M2.4 (label phase:M2.4) Tasks and company workflows. Done when: An agent checks out a work item and its comments can be listed, and a company workflow runs on the workflow engine against Company OS work items
- M2.5 (label phase:M2.5) Heartbeats fire reliably. Done when: Every heartbeat-enabled agent stays on the heartbeat schedule after a backend restart, each dispatch writes a backend log line, and the run token reaches the agent
- M2.6 (label phase:M2.6) Budgets enforced and costs recorded. Done when: An over-budget, paused or terminated agent is not dispatched (tests and host evidence), every LLM call records a cost event tied to its work item, and cost rollups never mix currencies
- M2.7 (label phase:M2.7) Approvals and board controls take effect. Done when: A hire, strategy or budget-override decision takes effect only through its post-decision hook (tests), there is one approval system, and pause and terminate survive a reload on a host
- M2.8 (label phase:M2.8) Audit trail and run supervision. Done when: Every activity record carries an actor type, a timed-out run shows in scorecards without error, a stalled run releases its claims, and the activity feed updates live
- M2.9 (label phase:M2.9) External agents: protocol and adapters. Done when: An external agent gets a protocol skill, passes a sign-in and version check before dispatch, and its declared work scope is enforced on every path
- M2.10 (label phase:M2.10) Portability, API docs, plugins and end-to-end proof. Done when: Export then import keeps the org chart and seed work, the Company OS routes have API reference docs, and a scripted run on a clean install passes company, hire, goals, tasks, heartbeat, budget stop, approval and audit
46% complete